Your Two Numbers

5%
Optional
$
Clear it and the verdict runs without the time line.
Enter an annual revenue between $500,000 and $100,000,000, or clear it.
The One Word Bill
—
—

—

What the loss becomes at your margin
The denied change order $88,730.70
New work needed to replace it —
Revenue required per dollar lost —
Months of your company's entire revenue —
The caseThe denied change order was 4.9% of the subcontract — and the sub recovered nothing. AMP Electrical v. W.M. Schultz Construction, Massachusetts Appeals Court, 2025.
What decided itA pre-bid addendum Q&A had already assigned the work to another trade. The reconciliation, not the excavation, is what cost the money.

SpecFinder reconciles every addendum against the base spec and cites what moved. Bring the book and the addenda.

Ask SpecFinder

Educational illustration anchored to one decided case. Not financial or legal advice, and not a prediction about your projects. Nothing you enter is stored.