The Spread Read
—
—

—

The field
Below the bidder median
—
—
Below your internal estimate
—
—
Gap to the next lowest bid
—
—
The linesScrutiny lines: 10% below the estimate (CMAA/UNC public-bidding literature) and 15–20% below the bidder median (Buildr — vendor). Two different references, reported separately, never averaged.
DocumentedA documented four-bid electrical package ran $130,000 to $230,000 on the same scope — the thread resolved in frustration because nothing existed to normalize the numbers (practitioner account, Mike Holt's Forum).